Tank Repair – Major Foundation Remediation & Tank Floor Replacement
This unique project required the existing tank to be elevated 4’ above its existing granular base. The 110’-0” diameter, multi-bay tank was…
This unique project required the existing tank to be elevated 4’ above its existing granular base. The 110’-0” diameter, multi-bay tank was…
Elite was contracted to supply and install a replacement carbon steel pontoon floating roof into an existing 120’-0” diameter tank. Following the…
Elite’s team was required to develop some creative engineering and operational solutions to support this high profile pulp mill shut down project…
When a Client has a unique problem, they require a unique solution! For this major repair project, Elite was contracted to restore…
For this project Elite had to replace the tank floor and annular plates, as well as provide a new foundation to elevate…
Due to extreme soil side erosion, Elite was contracted to replace the entire annular plate on a 110’ diameter boiler feed water…
An aging storage tank built in 1977 had undergone various service changes in its lifetime resulting in severe upper shell and roof…
This tank required multiple repairs to the foundation, tank floor and external floating roof. Various project constraints resulted in searching out alternative…
Unique safety challenges are not uncommon when it comes to tank repairs and maintenance. This project was unlike many due to the…
Engaged by the client prior to an out of service inspection created the opportunity to work with an evolving scope. Having a…
A unique project specifically in terms of location. Elite coordinated closely with the client to make arrangements to have equipments and material…