Field Tank Construction

Turn Around Tank Replacement

Elite Integrity Services was recently contracted to complete an entire tank replacement project inside our clients 5-day turn around window. Working closely with the client, Elite personnel developed a strategy to pre-build the replacement tank adjacent to the final location in advance, engineer the tank so that it could be safely hoisted into place and complete all necessary finishing prior to the turn around. Once the turn around commenced, Elite crews worked around the clock with the client's personnel and trusted industry partners to support dismantle, demolition and hoisting of the new tank onto the existing pad. All work was safely and successfully executed within the client's crucial project deadlines to bring the plant back into operation as planned.

Project Highlights:

  • (9) Pick Lift - Tank Weight of 85,000 lbs
  • (5) day turn around to remove process piping, complete demolition, clean up and re-installation of process piping for start up
  • Tank designed suitably to be hoisted by engineered lift lugs and bolted connections to safely lift onto existing tank pad

 

  • Project Size: 50'-0" Diameter x 10'-6" High
  • Project Type: New Construction
  • Completion Date: Summer 2022
  • Service: Raw Water Tank