Field Tank Construction

Turnkey Operations On A Liquid Sulphur Tank – Central AB

Customer required an 8500 MT (30,000BBL) molten sulphur tank to be constructed. Elite Integrity Services executed a large scale turnkey operation on this project from civil work, piling, concrete foundation, construction, hydrotest, insulation and final bolt up. This tank consisted of very precise complicated ABSA registered fittings that took a high level of expertise to install. This work was completed in the winter months during the heavy impacts of the Covid-19 pandemic and was executed safely and on schedule.

Project Highlights:

  • Double Jacketed Nozzles and Manways
  • High Pressure Piping
  • Self-supported Roof
  • Custom Heat Coil Assemblies
  • Complex Galvanized Roof Structure to provide customer safe access for servicing heat coils, steam straps and jacketed valves
  • Shell Insulation (5 inch Thick)
  • Project Size: 63' Diameter x 56' High
  • Project Type: New Construction
  • Completion Date: June 2021
  • Service: Liquid Sulphur

Gallery